      Actually, everything should be done by crane, but I guess management told them to use the forklifts cuz getting and assembling one on site costs a lot.

        • @0x4E4F@sh.itjust.worksOP
          link
          fedilink
          English
          615 days ago

          No, but tell that to Bob from management, who is not an engineer.

          I’ve been in situations like that. You just don’t do it. Also, explain why in written form and have that stamped and submitted.

        • Githyanki
          link
          fedilink
          English
          115 days ago

          I’m going to say less. They can do it by hand now!